G.R. No. 218009, September 21, 2016

MARVIN G. FELIPE AND REYNANTE L. VELASCO, Petitioners, v. DANILO DIVINA TAMAYO KONSTRACT, INC. (DDTKI) AND/OR DANILO DIVINA TAMAYO, PRESIDENT/OWNER, Respondent.

D E C I S I O N

MENDOZA, J.:

This is a Petition for Review on Certiorari under Rule 45 of the Rules of Court seeking the annulment of the March 27, 2013 Decision1 and the March 26, 2015 Resolution2 of the Court of Appeals (CA) in CA-G.R. SP No. 123413, which affirmed the September 30, 2011 Decision3 and the December 7, 2011 Resolution4 of the National Labor Relations Commission (NLRC), in a case of illegal dismissal filed by petitioners Marvin G. Felipe (Felipe) and Reynante L. Velasco (Velasco) against respondents Danilo Divina Tamayo Konstract, Inc. (DDTKI) and its president/owner, Danilo Divina Tamayo (Tamayo).

The Antecedents:

DDTKI hired Felipe as Formworks Aide on December 19, 2005, and Velasco as Warehouse Aide on March 14, 2007. Felipe and Velasco claimed regular employment status for having continuously worked for DDTKI until September 2010 when they were no longer given working assignments. They wrote a letter, dated September 28, 2010, to the respondents inquiring about their employment status and why they were not transferred to the Glorietta Project which supposedly started on September 17, 2010, based on a document denominated as a Manpower Requisition Form (MRF). The respondents, however, did not reply to their letter.5chanrobleslaw

On October 12, 2010, Felipe and Velasco filed their complaint for illegal dismissal and non-payment of service incentive leave and 13th month pay against the respondents before the arbitration branch of the NLRC.6chanrobleslaw

The respondents, on the other hand, claimed that the petitioners were former project employees of DDTKI who were hired for a particular project. They presented various project employment contracts duly signed by Felipe and Velasco to support their claim that these employees were hired for specific construction projects for a specific period, and that they were informed of the nature and duration of their employment from the beginning of their engagement.7chanrobleslaw

The respondents further averred that as of September 2010, Felipe and Velasco were not rehired as the company "did not need any more workers after the completion of their respective projects." After the completion of their last project, the US Embassy New Office Annex 1 Project (MNOX-1), Felipe and Velasco were not rehired and their termination was reported to the Department of Labor and Employment (DOLE) as "completion of phase of work." DDTKI stressed that they were never employed for the Glorietta Project and the illegally obtained MRF, a confidential document of DDTKI, did not serve as its employment contract with Felipe and Velasco.8chanrobleslaw

At the Labor Level

On March 28, 2011, the Labor Arbiter (LA) rendered his decision9 dismissing the complaint for utter lack of merit. The LA found that Felipe and Velasco were project employees as borne out by their contracts of employment and, thus, ruled that they were not illegally dismissed. It was pointed out that:ChanRoblesVirtualawlibrary

A close examination of their respective employment contracts would readily reveal that they specifically mention the duration of the contract for a specific client. On the last part thereof, there is a specific provision that the period indicated shall serve as a notice to the employee for the termination of the project employment.10 [Emphasis supplied]
On appeal, the NLRC affirmed the ruling of the LA that the termination of the services of Felipe and Velasco on the ground of the expiration of their project employment contracts was legitimate and valid. The decision was, however, modified as DDTKI was directed to pay Felipe and Velasco their proportionate 13th month pay. The latter moved for reconsideration, but their motion was denied.

At the CA Level

Aggrieved, petitioners filed their petition for certiorari before the CA. In its assailed Decision, dated March 27, 2013, the CA denied the petition after finding that the NLRC did not act whimsically or arbitrarily to warrant the nullification of its judgment. Further, the CA reiterated that the length of service and the continuous rehiring of petitioners did not automatically accord them regular status. DDTKI contracted petitioners for specific undertakings, the scope and duration of which had been determined and made known to them. Their termination from work was found by the CA not illegal, as the specific project for which they were hired merely expired. The CA stated that the MRF, an internal memo for administrative purposes, did not constitute a project employment contract between DDTKI and petitioners. It, therefore, could not serve as basis for the rehiring of petitioners.11 Thus, the CA disposed the case as follows:ChanRoblesVirtualawlibrary
WHEREFORE, the instant Petition is DENIED and the assailed Decision dated 30 September 2011 and Resolution dated 07 December 2011 of the National Labor Relations Commission are hereby AFFIRMED in toto.

SO ORDERED.12chanroblesvirtuallawlibrary
Unsatisfied, petitioners moved for reconsideration, but their motion was denied in the assailed CA Resolution, dated March 26, 2015, for being a mere rehash of the arguments that were already raised and passed upon in their petition.

Hence, the present petition raising the following
ISSUES

I.

WHETHER OR NOT PETITIONERS WERE REGULAR (WORK POOL) EMPLOYEES OF THE PRIVATE RESPONDENTS.

II.

WHETHER OR NOT PETITIONERS WERE ILLEGALLY DISMISSED.

III.

WHETHER OR NOT PETITIONERS ARE ENTITLED TO ALL THEIR MONETARY CLAIMS, INCLUDING MORAL AND EXEMPLARY DAMAGES AND ATTORNEY'S FEES.
13chanroblesvirtuallawlibrary
Petitioners contend that there was grave abuse of discretion amounting to lack or in excess of jurisdiction on the part of the CA in denying their petition for certiorari and their motion for reconsideration despite the evidence they presented in support of their petition. They argue that contrary to the findings of the CA, it cannot be said that their employment was project-based because there was no project contract presented by the respondents supporting the one (1) month duration of their employment contract and stating that the phase of the project ended on particular dates mentioned in their employment contracts. They insist that they were regular employees considering that they had been employed to perform activities which were usually necessary or desirable in the usual business or trade of their employer, continuously for a period of four (4) years, and contracted for a total of seven (7) successive projects. Felipe's position as Formworks Aide and Velasco's as Warehouse Aide clearly required them to perform tasks inculcated in the usual operation of DDTKI's construction business. As regular employees, they claim that they were entitled to security of tenure and could only be dismissed for a just or authorized cause. The alleged cause of dismissal (completion of project) was not a valid cause under Articles 282 and 283 of the Labor Code. Thus, petitioners posit that they were entitled to reinstatement to their former or equivalent positions without loss of seniority rights and other privileges; to their full back wages, inclusive of allowances; and to their other benefits or their monetary equivalent computed from the time their compensations were withheld up to the time of their actual reinstatement. Petitioners also argue that having rendered uninterrupted service for four (4) years, they were, under the law, entitled to service incentive leave pay three (3) years backward from the filing of the case.14chanrobleslaw

Respondents' Position

Respondents DDKTI and Tamayo (respondents), in their Comment,15 dated August 24, 2015, counter that the petition should be dismissed because grave abuse of discretion is not the proper subject matter of a petition under Rule 45. Even assuming that grave abuse of discretion may be used as basis, petitioners failed to show grave abuse on the part of the CA. Respondents insist that petitioners were project employees because they were contracted to work for a specific task not permanently continuing within a particular period that was already determined at the time of their hiring. An uninterrupted service for four (4) years did not automatically make them regular employees. Hence, they were not entitled to reinstatement, back wages, moral and exemplary damages, and attorney's fees.

Basically, petitioners are asking the Court to resolve whether the CA correctly ruled that there was no grave, abuse of discretion on the part of the NLRC, thus, affirming the finding that petitioners were project employees.

The Court's Ruling

The issue as to whether petitioners were project employees or regular employees is factual in nature. Well-entrenched is the rule in our jurisdiction that only questions of law may be entertained by this Court in a petition for review on certiorari. Moreover, the factual findings of quasi-judicial bodies like the NLRC, if supported by substantial evidence, are accorded respect and even finality by this Court, more so when they coincide with those of the LA.16 Such factual findings are given more weight when the same are affirmed by the CA as in this case.

There is no reason to depart from these rules. The CA did not err in affirming the findings of the NLRC that petitioners were project employees of DDTKI. Article 280 of the Labor Code, which distinguishes a project employee from a regular employee, provides:ChanRoblesVirtualawlibrary
Art. 280. Regular and casual employment. The provisions of written agreement to the contrary notwithstanding and regardless of the oral agreement of the parties, an employment shall be deemed to be regular where the employee has been engaged to perform activities which are usually necessary or desirable in the usual business or trade of the employer, except where the employment has been fixed for a specific project or undertaking the completion or termination of which has been determined at the time of the engagement of the employee, or where the work or services to be performed is seasonal in nature and the employment is for the duration of the season.

An employment shall be deemed to be casual if it is not covered by the preceding paragraph: Provided, That any employee who has rendered at least one year of service, whether such service is continuous or broken, shall be considered a regular employee with respect to the activity in which he is employed and his employment shall continue while such activity exists. [Emphasis supplied]
A project employee is assigned to a project which begins and ends at determined or determinable times. Unlike regular employees who may only be dismissed for just and/or authorized causes under the Labor Code, the services of employees who are hired as "project employees" may be lawfully terminated at the completion of the project. According to jurisprudence, the principal test for determining if particular employees are properly characterized as "project employees," as distinguished from "regular employees," is whether or not the employees are assigned to carry out a "specific project or undertaking," the duration (and scope) of which are specified at the time they are engaged for that project. The project can either be (1) a particular job or undertaking that is within the regular or usual business of the employer company, but which is distinct and separate, and identifiable as such, from the other undertakings of the company; or (2) a particular job or undertaking that is not within the regular business of the corporation.17chanrobleslaw

In this case, the LA, the NLRC and the CA were one in finding that petitioners were project employees hired by DDTKI for a specific task within a particular period already determined at the time of their hiring as evidenced by their employment contracts.

As correctly noted by the CA, petitioners' employment was terminated due to the expiration of the period for which they were contracted. Considering that their employment contract for the US Embassy New Office Annex 1 Project (MNOX-1) had been terminated on September 18, 2010, the CA correctly ruled that their termination from work was not illegal but that the project for which they were hired merely expired.

On their contention that they were regular employees due to their uninterrupted service for DDTKI for four (4) years and the continuous employment contract renewal every month, petitioners are mistaken. In Aro v. NLRC,18 the Court explained:ChanRoblesVirtualawlibrary
[T]he length of service or the re-hiring of construction workers on a project-to-project basis does not confer upon them regular employment status, since their, re-hiring is only a natural consequence of the fact that experienced construction workers are preferred. Employees who are hired for carrying out a separate job, distinct from the other undertakings of the company, the scope and duration of which has been determined and made known to the employees at the time of the employment, are properly treated as project employees and their services may be lawfully terminated upon the completion of a project. xxx.19 [Emphasis supplied]
Therefore, being project employees who have been validly terminated by reason of the completion of the specific project, MNOX-1, for which they were hired, petitioners Felipe and Velasco are not entitled to reinstatement and back wages.

On the issue of non-payment of service incentive leave, the Court rules that petitioners are not entitled to this benefit either. Based on records and as correctly noted by respondents, they have not rendered at least one year of continuous service.

WHEREFORE, the petition is DENIED.

SO ORDERED.chanRoblesvirtualLawlibrary

Brion, (Acting Chairperson), Del Castillo, and Leonen, JJ., concur.
Carpio, J., on official leave.

Endnotes:


1 Penned by Associate Justice Jane Aurora C. Lantion with Associate Justices Vicente S.E. Veloso, and Eduardo B. Peralta, Jr. concurring. Rollo, pp. 31-41.

2 Associate Justice Samuel H. Gaerlan, additional member due to Associate Justice Veloso's retirement. Id. at 43-44.

3 Id. at 64-73.

4 Id. at 75-76.

5 Id. at 32-33.

6 Id. at 64-65.

7 Id. at 33-34.

8 Id. at 34.

9 Id. at 78-87. Penned by Labor Arbiter Antonio R. Macam.

10 Id. at 35.

11 Id. at 39-40.

12 Id. at 40.

13 Id. at 15.

14 Id. at 17-24.

15 Id. at 513-543.

16Oasay, Jr. v. Palacio del Gobernador Condominium Corporation, et al., 681 Phil. 69, 79 (2012).

17Gadia v. Sykes Asia, Inc., G.R. No. 209499, January 28, 2015, 748 SCRA 633, 643, citing Omni Hauling Services, Inc. v. Bon, G.R. No. 199388, September 3, 2014, 734 SCRA 270, 279.

18 683 Phil. 605 (2012).

19 Id. at 614, citing Hanjin Heavy Industries and Co., Ltd v. Ibaez, 578 Phil. 497, 510 (2008).



Back to Home | Back to Main




















chanrobles.com





ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com






September-2016 Jurisprudence                 

  • G.R. No. 211608, September 07, 2016 - PEOPLE OF THE PHILIPPINES, Plaintiff-Appellee, v. MENARDO BOMBASI Y VERGARA, Accused-Appellant.

  • G.R. No. 195975, September 05, 2016 - TAINA MANIGQUE-STONE, Petitioner, v. CATTLEYA LAND, INC., AND SPOUSES TROADIO B. TECSON AND ASUNCION ORTALIZ-TECSON, Respondents.

  • G.R. No. 212171, September 07, 2016 - PEOPLE OF THE PHILIPPINES, Plaintiff-Appellee, v. MERCURY DELA CRUZ ALIAS "DEDAY," Accused-Appellant.

  • A.C. No. 10565, September 07, 2016 - PROSECUTOR RHODNA A. BACATAN, Complainant, v. ATTY. MERARI D. DADULA, Respondent.

  • A.C. No. 7045, September 05, 2016 - THE LAW FIRM OF CHAVEZ MIRANDA ASEOCHE REPRESENTED BY ITS FOUNDING PARTNER, ATTY. FRANCISCO I. CHAVEZ, Complainant, v. ATTYS. RESTITUTO S. LAZARO AND RODEL R. MORTA, Respondents.

  • G.R. No. 204423, September 14, 2016 - PHILIPPINE SCIENCE HIGH SCHOOL-CAGAYAN VALLEY CAMPUS, Petitioner, v. PIRRA CONSTRUCTION ENTERPRISES, Respondent.

  • I.P.I. No. 16-244-CA-J, September 06, 2016 - Re: VERIFIED COMPLAINT OF CATALINA Z. ALILING AGAINST ASSOCIATE JUSTICE MA. LUISA C. QUIJANO-PADILLA, COURT OF APPEALS, MANILA RELATIVE TO CA-G.R. CV NO. 103042

  • G.R. No. 203576, September 14, 2016 - NAGA CENTRUM, INC., REPRESENTED BY AIDA KELLY YUBUCO, Petitioner, v. SPOUSES RAMON J. ORZALES AND NENITA F. ORZALES, Respondent.

  • G.R. No. 192754, September 07, 2016 - LEONIS NAVIGATION CO., INC. AND WORLD MARINE PANAMA S.A., Petitioners, v. EDUARDO C. OBRERO AND MERCEDITA P. OBRERO, Respondents.

  • G.R. No. 181387, September 05, 2016 - CAMERON GRANVILLE 3 ASSET MANAGEMENT, INC., Petitioner, v. UE MONTHLY ASSOCIATES, UEAMI WORKERS UNION NFL AND ALFREDO BASI, Respondent.

  • G.R. No. 206808-09, September 07, 2016 - LOCAL WATER UTILITIES ADMINISTRATION EMPLOYEES ASSOCIATION FOR PROGRESS (LEAP), MELANIO B. CUCHAPIN II, GREARDO* G. PERU, ROLAND S. CABAHUG, GLORIA P. VELASQUEZ, ERLINDA G. VILLANUEVA, TEODORO M. REYNOSO, FERNANDO L. NICANDRO, JOSEPHINE P. SIMENE, LAMBERTO R. RIVERA, REYNALDO M. VIDA, and RUCTICO** B. TUTOL, Petitioners, v. LOCAL WATER UTILITIES ADMINISTRATION (LWUA) and DEPARTMENT OF BUDGET AND MANAGEMENT, Respondents.

  • G.R. No. 210798, September 14, 2016 - PEOPLE OF THE PHILIPPINES, Plaintiff-Appellee, v. BEVERLY VILLANUEVA Y MANALILI @ BEBANG, Accused-Appellant.

  • G.R.No. 186199, September 07, 2016 - EDGARDO A. QUILO AND ADNALOY VILLAHERMOSA, Petitioners, v. TEODULA BAJAO, Respondent.

  • G.R. No. 187942, September 07, 2016 - THE ROMAN CATHOLIC BISHOP OF TUGUEGARAO, Petitioner, v. FLORENTINA PRUDENCIO, NOW DECEASED, SUBSTITUTED BY HER HEIRS, NAMELY: EXEQUIEL, LORENZO, PRIMITIVO, MARCELINO, JULIANA, ALFREDO AND ROSARIO, ALL SURNAMED DOMINGO; AVELINA PRUDENCIO, ASSISTED BY HER HUSBAND VICTORIANO DIMAYA; ERNESTO PENALBER AND RODRIGO TALANG; SPOUSES ISIDRO CEPEDA AND SALVACION DIVINI, NOW DECEASED, SUBSTITUTED BY HER HEIRS, NAMELY: MARCIAL, PEDRO AND LINA, ALL SURNAMED CEPEDA, Respondents.

  • A.C. No. 10574 (Formerly CBD Case No. 11-3047), September 20, 2016 - PATRICK R. FABIE, Complainant, v. ATTY. LEONARDO M. REAL, Respondents.

  • G.R. No. 192132, September 14, 2016 - HEIRS OF ZOSIMO Q. MARAVILLA, NAMELY, ZOSIMO W. MARAVILLA, JR., YVETTE MARAVILLA AND RICHARD MARAVILLA, REPRESENTED BY ZOSIMO W. MARAVILLA, JR., Petitioners, v. PRIVALDO TUPAS, Respondent.

  • G.R. No. 206629, September 14, 2016 - NARCISO T. MATIS, Petitioner, v. MANILA ELECTRIC COMPANY, Respondent.

  • G.R. No. 210940, September 06, 2016 - SOCIAL SECURITY SYSTEM, Petitioner, v. COMMISSION ON AUDIT, Respondent.

  • G.R. No. 201320, September 14, 2016 - WILSON T. LIM, Petitioner, v. OFFICE OF THE DEPUTY OMBUDSMAN FOR THE MILITARY AND OTHER LAW ENFORCEMENT OFFICES (MOLEO) AND P/S INSP. EUSTIQUIO FUENTES, Respondents.

  • G.R. No. 219815, September 14, 2016 - J.O.S. MANAGING BUILDERS, INC. AND EDUARDO B. OLAGUER, Petitioners, v. UNITED OVERSEAS BANK PHILIPPINES (FORMERLY KNOWN AS WESTMONT BANK), EMMANUEL T. MANGOSING AND DAVID GOH CHAI ENG, Respondents.

  • G.R. No. 220732, September 06, 2016 - ELMER G. SINDAC @ "TAMER," Petitioner, v. THE PEOPLE OF THE PHILIPPINES, Respondent.

  • G.R. Nos. 190015 & 190019, September 14, 2016 - GERALDINE MICHELLE B. FALLARME AND ANDREA MARTINEZ-GACOS, Petitioners, v. SAN JUAN DE DIOS EDUCATIONAL FOUNDATION, INC., CHONA M. HERNANDEZ, VALERIANO ALEJANDRO III, SISTER CONCEPTION GABATINO, D.C., AND SISTER JOSEFINA QUIACHON, D.C., Respondent.

  • G.R. No. 214238, September 14, 2016 - PEOPLE OF THE PHILIPPINES, Plaintiff-Appellee, v. ESMAEL ZACARIA Y WAGAS, Accused-Appellant.

  • G.R. No. 191170, September 14, 2016 - CAMERON GRANVILLE 3 ASSET MANAGEMENT, INC., Petitioner, v. FIDEL O. CHUA AND FILIDEN REALTY AND DEVELOPMENT CORP., Respondent.

  • G.R. No. 219855, September 06, 2016 - PEOPLE OF THE PHILIPPINES, Plaintiff-Appellee, v. ROMEO LINTAG Y LAUREOLA, Accused-Appellant.

  • G.R. No. 199397, September 14, 2016 - PEOPLE OF THE PHILIPPINES, Plaintiff-Appellee, v. DARWIN GITO Y CORLIN, ACCUSED-APPELLANT., Respondent.

  • G.R. No. 194561, September 14, 2016 - DRUGSTORES ASSOCIATION OF THE PHILIPPINES, INC. AND NORTHERN LUZON DRUG CORPORATION, Petitioners, v. NATIONAL COUNCIL ON DISABILITY AFFAIRS; DEPARTMENT OF HEALTH; DEPARTMENT OF FINANCE; BUREAU OF INTERNAL REVENUE; DEPARTMENT OF THE INTERIOR AND LOCAL GOVERNMENT; AND DEPARTMENT OF SOCIAL WELFARE AND DEVELOPMENT, Respondent.

  • G.R. No. 190271, September 14, 2016 - TRANSIMEX CO., Petitioner, v. MAFRE ASIAN INSURANCE CORP., Respondent.

  • G.R. No. 182604, September 27, 2016 - DR. ROLANDO B. MANGUNE, DR. RENE A. ARCE AND EMMA E. TA�AFRANCA, IN THEIR RESPECTIVE PERSONAL CAPACITIES AND AS ATTORNEYS-IN-FACT FOR AND IN BEHALF OF DR. VIRGINIA M. AGUILAS, ROLANDO R. ANATALIO, DR. LEA M. DE LEON-ASI, CATALINO N. ATANACIO, JR., JULIANA M. BATALLER, MA. LUISA B. CA�EZA, LILIAN C. CANILAO, RANIEL S. CAPADA, FLORENDO A. DAYUS, JENNIFER D. PAGULAYAN, BIENVENIDO C. DE VILLA, JOSE A. DELOS REYES, CYNTHIA A. DIAZ, ANNA LEAH D. DIPATUAN, MADELAINE M. ESTOCAPIO, DR. MARIA SONIA YEE-FESTIN, MARIO E. FLORENDO, RUEL E. FORTUNADO, NATIVIDAD A. GAMIAO, IRMA Q. ANDAL, CHARITO C. LAZAM, AGNES R. LOVINDINO, EVELYN M. MABAG, RECHILDA B. MACAFE, ZENAIDA M. MADIANGKIT, ANGELICA T. MALAZARTE, DOMINGO P. MANAY, DR. EDGAR ORVEN M. MORTEL, SATURNINO E. QUIBAN, MARITES J. RAMOS, DR. MELINDA S.L. A. RAZALAN, BAITONGGAL L. SAUDAGAL, DR. JOHN ALBERT V. TABLIZO, JULIETA T. TERANIA, ANNIE B. TRINIDAD, JUDY T. AVNER, DR. ROMEO F. UY, AVELONA A. VEA, MINVILUZ G. VERA CRUZ, PE�AFLOR M. VILLAFLOR, JR., AND DR. LEOPOLDO P. SISON, JR., ALL OF TAGUIG-PATEROS DISTRICT HOSPITAL, Petitioners, v. HONORABLE SECRETARY EDUARDO ERMITA, IN HIS OFFICIAL CAPACITY AS EXECUTIVE SECRETARY, HONORABLE SECRETARY FRANCISCO DUQUE III, IN HIS OFFICIAL CAPACITY AS SECRETARY OF THE DEPARTMENT OF HEALTH, THE CITY GOVERNMENT OF TAGUIG AS REPRESENTED BY ITS MAYOR, HONORABLE SIGFRIDO R. TINGA, AND THE MUNICIPAL GOVERNMENT OF PATEROS, AS REPRESENTED BY ITS MAYOR, HONORABLE ROSENDO CAPCO, Respondent.

  • G.R. No. 210200, September 13, 2016 - JULIET B. DANO, Petitioner, v. COMMISSION ON ELECTIONS AND MARIE KAREN JOY B. DIGAL, Respondents.; MARIA EMILY D. DAGAANG, Petitioner-Intervenor.

  • A.C. No. 11095 [Formerly CBD Case No. 11-3140], September 20, 2016 - EUFEMIA A. CAMINO, Complainant, v. ATTY. RYAN REY L. PASAGUI, Respondent.

  • G.R. No. 188952, September 21, 2016 - PE�AFRANCIA SHIPPING CORPORATION AND SANTA CLARA SHIPPING CORPORATION, Petitioners, v. 168 SHIPPING LINES, INC., Respondent.

  • A.C. No. 11238, September 21, 2016 - ATTY. MYLENE S. YUMUL-ESPINA, Complainant, v. ATTY. BENEDICTO D. TABAQUERO, Respondent.

  • G.R. No. 187922, September 21, 2016 - MARPHIL EXPORT CORPORATION AND IRENEO LIM, Petitioners, v. ALLIED BANKING CORPORATION, SUBSTITUTED BY PHILIPPINE NATIONAL BANK, Respondent.

  • G.R. No. 188646, September 21, 2016 - GEORGE C. CORDERO, Petitioner, v. BOARD OF NURSING, Respondent.

  • A.C. No. 10150, September 21, 2016 - GINA E. ENDAYA, Complainant, v. ATTY. EDGARDO O. PALAY, Respondent.

  • G.R. No. 185765, September 28, 2016 - PHILIPPINE ECONOMIC ZONE AUTHORITY, Petitioner, v. PILHINO SALES CORPORATION, Respondent.

  • G.R. No. 184237, September 21, 2016 - HENRY H. TENG, Petitioner, v. LAWRENCE C. TING, EDMUND TING AND ANTHONY TING, Respondent.

  • G.R. No. 222740, September 28, 2016 - ST. LUKE'S COLLEGE OF MEDICINE-WILLIAM H. QUASHA MEMORIAL FOUNDATION, DR. BRIGIDO L. CARANDANG, AND DR. ALEJANDRO P. ORTIGAS Petitioners, v. SPOUSES MANUEL AND ESMERALDA PEREZ AND SPOUSES ERIC AND JURISITA QUINTOS, Respondents.

  • G.R. No. 211680, September 21, 2016 - PEOPLE OF THE PHILIPPINES, Appellee, v. BELBAN SIC-OPEN Y DIMAS, Appellant.

  • G.R. No. 193837, September 21, 2016 - PEOPLE OF THE PHILIPPINES, Plaintiff-Appellee, v. RENATO M. PANGAN, Accused-Appellant.

  • G.R. No. 224804, September 21, 2016 - EFREN R. LEYNES, Petitioner, v. PEOPLE OF THE PHILIPPINES, Respondent.

  • G.R. No. 215072, September 07, 2016 - PHILIPPINE NATIONAL BANK, Petitioner, v. HEIRS OF THE LATE IRENEO AND CARIDAD ENTAPA, NAMELY: ROSARIO ENTAPA-ORPEZA, JULIANNE E. HAMM,1 CERINA G. ENTAPA, WINSTON G. ENTAPA (DECEASED) REPRESENTED BY HIS SPOUSE, NINFA LAMISTOZA-ENTAPA, FRANKLIN G. ENTAPA, MARINA E. SCHACHT, AND ELVIRA G. ENTAPA, Respondents.

  • G.R. No. 201354, September 21, 2016 - PABLO M. PADILLA, JR. AND MARIA LUISA P. PADILLA, Petitioners, v. LEOPOLDO MALICSI, LITO CASINO, AND AGRIFINO GUANES, Respondents.

  • G.R. No. 183947, September 21, 2016 - RIZAL COMMERCIAL BANKING CORPORATION, Petitioner, v. TEODORO G. BERNARDINO, Respondent.

  • G.R. No. 204891, September 14, 2016 - PEOPLE OF THE PHILIPPINES, Appellee, v. REYNALDO ABAYON Y APONTE, Appellant.

  • A.C. No. 11064, September 27, 2016 - BIENVENIDA FLOR SUAREZ, Complainant, v. ATTY. ELEONORA. MARAVILLA-ONA, Respondent.

  • A.M. No. P-09-2621 [Formerly OCA-I.P.I. No. 08-2939-P], September 20, 2016 - OFFICE OF THE COURT ADMINISTRATOR, Complainant, v. EDUARDO T. UMBLAS, LEGAL RESEARCHER, REGIONAL TRIAL COURT, BRANCH 33, BALLESTEROS, CAGAYAN, Respondent.

  • G.R. No. 208979, September 21, 2016 - GOVERNMENT SERVICE INSURANCE SYSTEM, Petitioner, v. ROGELIO F. MANALO, Respondent.

  • A.C. No. 11099, September 27, 2016 - LILY FLORES-SALADO, MINDA FLORES LURA, AND FE V. FLORES, Complainants, v. ATTY. ROMAN A. VILLANUEVA, JR. Respondent.

  • A.C. No. 7348, September 27, 2016 - ROUEL YAP PARAS, Complainant, v. ATTY. JUSTO P. PARAS, Respondent.

  • G.R. No. 208067, September 14, 2016 - PEOPLE OF THE PHILIPPINES, Appellee, v. RONNIE R. LIBRIAS, Appellant.

  • G.R. No. 211553, September 13, 2016 - LEANDRO B. VERCELES, JR., Petitioner, v. COMMISSION ON AUDIT, Respondent.

  • G.R. No. 208089, September 28, 2016 - PHILIPPINE TRANSMARINE CARRIERS, INC., STEALTH MARITIME CORPORATION AND CARLOS SALINAS, Petitioners, v. CASIANO F. SALADAS, JR., Respondent.

  • G.R. No. 217356, September 07, 2016 - DOROTEO C. GAERLAN, (DECEASED) SUBSTITUTED BY HIS SON, RAYMOND G. GAERLAN, Petitioner, v. PHILIPPINE NATIONAL BANK, Respondent.

  • G.R. No. 222424, September 21, 2016 - FONTANA DEVELOPMENT CORP., DENNIS PAK AS GENERAL MANAGER, PASTOR ISAAC AS DIRECTOR OF HUMAN RESOURCES, CHRIS CHENG* AS DEPUTY GROUP FINANCIAL CONTROLLER, JESUS CHUA, REPRESENTATIVE MICHAEL FELICIANO, ALMA EREDIANO, LEILANI VALIENTE, MAN CHOI AS GROUP FINANCIAL CONTROLLER, AND JAIME VILLAREAL AS CHIEF ENGINEER, Petitioners, v. SASCHA VUKASINOVIC, Respondent.

  • G.R. No. 221864, September 14, 2016 - CELERNA CALAYAG, AMELIA ORFIANO, MARILYN HIBE, ERNESTO CLARIN, NARCISO UNGSOD, BONIFACIO TORIDA, BOB ILLUT, EVELYN BAJET, ELORDE ILUSTRISIMO, ENRICO DETIQUEZ, JAIME CASTRO, JOSEFINA DAMALERIO, CARIDAD LERUM, NOVA FAJARDO, DANILO DELA CRUZ, ALBERTO FAUSTO, ESTELLA GELLI, KATHERINE DELA CRUZ, HEIDEE LAUREL, NISSAN LAUREL, VICENTE CHUA, ARMELA MARTIN, MELINDA BATIANCILA, GEMMA REBAYA, PRECIOUS ILUSTRISIMO, SOSAN LISBO, MARLON TRABALLO, NIMFA DANNUG, MARILYN LABORTE, SONIA MANZANILLA, LOURDES PARBA, ADELINA ALIPIN, JONATHAN BASA, MARIA LIZA CABARQUIL, RICHARD FAJICULAY, RICARDO HILARIO AND JONATHAN TESSLER, Petitioners, v. SULPICIO LINES, INC. (NOW KNOWN AS PHILIPPINE SPAN ASIA CARRIER CORPORATION, DOING BUSINESS UNDER THE NAME AND STYLE OF "SPAN ASIA CARRIER") [FORMERLY: SULPICIO LINES, INC.], Respondent.

  • G.R. No. 221047, September 14, 2016 - MICHAEL A. ONSTOTT, Petitioner, v. UPPER TAGPOS NEIGHBORHOOD ASSOCIATION, INC., Respondent.

  • A.C. No. 11323, September 14, 2016 - NICOLAS ROBERT MARTIN EGGER, Complainant, v. ATTY. FRANCISCO P. DURAN, Respondent.

  • G.R. No. 221241, September 14, 2016 - MARIO N. FELICILDA, Petitioner, v. MANCHESTEVE H. UY, Respondent.

  • A.C. No. 9912, September 21, 2016 - DATU REMIGIO M. DUQUE JR., Complainant, v. COMMISSION ON ELECTIONS CHAIRMAN SIXTO S. BRILLANTES, JR., COMMISSIONERS LUCENITO N. TAGLE, ELIAS R. YUSOPH, AND CHRISTIAN ROBERT S. LIM; ATTYS. MA. JOSEFINA E. DELA CRUZ, ESMERALDA A. AMORA-LADRA, MA. JUANA S. VALLEZA, SHEMIDAH G. CADIZ, AND FERNANDO F. COT�-OM; AND PROSECUTOR NOEL S. ADION, Respondent.

  • G.R. No. 212157, September 28, 2016 - PEOPLE OF THE PHILIPPINES, Plaintiff-Appellee, v. RODRIGO RUSCO, ACCUSED-APPELLANT., Respondent.

  • G.R. No. 221538, September 20, 2016 - RIZALITO Y. DAVID, Petitioner, v. SENATE ELECTORAL TRIBUNAL AND MARY GRACE POE-LLAMANZARES, Respondents.

  • G.R. No. 207147, September 14, 2016 - EMELITA BASILIO GAN, Petitioner, v. REPUBLIC OF THE PHILIPPINES, Respondent.

  • G.R. No. 213699, September 28, 2016 - THE OFFICE OF THE OMBUDSMAN, Petitioner, v. P/SUPT. ROGER JAMES BRILLANTES, PO3 PETER PAUL PABLICO, AND PO1 NOEL FABIA, Respondents.; G.R. No. 215008 - THE OFFICE OF THE OMBUDSMAN, Petitioner, v. POLICE SENIOR INSPECTOR2 DANTE G. YANG, Respondent.

  • G.R. No. 223852, September 14, 2016 - EDNA ROQUE ALEGUELA, FELIPE GONZALES, DOLORES COCHESA, LUISA CAGALINGAN, REYNALDO JUNSAY, BONIFACIA RODRIQUEZ, CONEY CERDENA, AND ALL PERSONS CLAIMING RIGHTS UNDER THEM, Petitioners, v. EASTERN PETROLEUM CORPORATION AND J&M PROPERTIES AND CONSTRUCTION CORPORATION, Respondents.

  • G.R. No. 205721, September 14, 2016 - HARTE-HANKS PHILIPPINES, INC., Petitioner, v. COMMISSIONER OF INTERNAL REVENUE, Respondent.

  • G.R. No. 225141, September 26, 2016 - ENERGY REGULATORY COMMISSION, Petitioner, v. HON. GREGORIO L. VEGA, JR., PRESIDING JUDGE, REGIONAL TRIAL COURT, BRANCH 157, PASIG CITY, AND MANILA ELECTRIC COMPANY, Respondents.

  • G.R. No. 205200, September 21, 2016 - PEOPLE OF THE PHILIPPINES, Appellee, v. LEONARDO CRUZ Y ROCO, Appellant.

  • G.R. No. 205871, September 28, 2016 - RUEL TUANO Y HERNANDEZ, Petitioner, v. PEOPLE OF THE PHILIPPINES, Respondent.

  • A.C. No. 11121, September 13, 2016 - DELIA LIM, Complainant, v. ATTY. AQUILINO MEJICA, Respondent.

  • G.R. No. 191537, September 14, 2016 - PAULINO M. ALECHA, FELIX B. UNABIA, RICARDO A. TOLINO AND MARIO A. CATANES, Petitioners, v. JOSE L. ATIENZA JR., THE DEPARTMENT OF ENVIRONMENT AND NATURAL RESOURCES (DENR), MICHAEL L. ROMERO AND BOARD OF DIRECTORS OF 168 FERRUM PACIFIC MINING CORPORATION, Respondent.

  • G.R. No. 213418, September 21, 2016 - ALFREDO S.RAMOS, CONCHITA S. RAMOS, BENJAMIN B. RAMOS, NELSON T. RAMOS AND ROBINSON T. RAMOS, Petitioners, v. CHINA SOUTHERN AIRLINES CO. LTD., Respondent.

  • G.R. No. 220605, September 21, 2016 - COCA-COLA FEMSA PHILIPPINES, INC.,* Petitioner, v. BACOLOD SALES FORCE UNION-CONGRESS OF INDEPENDENT ORGANIZATION-ALU, Respondent.

  • G.R. No. 190187, September 28, 2016 - THE PHILIPPINE GEOTHERMAL, INC. EMPLOYEES UNION, Petitioner, v. UNOCAL PHILIPPINES, INC. (NOW KNOWN AS CHEVRON GEOTHERMAL PHILIPPINES HOLDINGS, INC.), Respondent.

  • G.R. No. 198350, September 14, 2016 - ATTY. MARCOS D. RISONAR, JR., Petitioner, v. COR JESU COLLEGE AND/OR EDGARDO S. ESCURIL, Respondents.

  • G.R. No. 172507, September 14, 2016 - NATIONAL POWER CORPORATION, Petitioner, v. SPS. MARGARITO ASOQUE AND TARCINIA ASOQUE, Respondents.

  • A.C. No. 10782, September 14, 2016 - ATTY. DELIO M. ASERON, Complainant, v. ATTY. JOSE A. DI�O, JR., Respondent.

  • G.R. No. 223076, September 13, 2016 - PILAR CA�EDA BRAGA, PETER TIU LAVINA, ANTONIO H. VERGARA, BENJIE T. BADAL, DIOSDADO ANGELO A. MAHIPUS, AND SAMAL CITY RESORT OWNERS ASSOCIATION, INC. (SCROA), Petitioners, v. HON. JOSEPH EMILIO A. ABAYA, IN HIS CAPACITY AS SECRETARY OF THE DEPARTMENT OF TRANSPORTATION AND COMMUNICATIONS, DEPARTMENT OF TRANSPORTATION AND COMMUNICATIONS (DOTC), PRE-QUALIFICATION, BIDS AND AWARDS COMMITTEE (PBAC) AND PHILIPPINE PORTS AUTHORITY (PPA), Respondents.

  • G.R. No. 204659, September 19, 2016 - JESTER MABUNOT, Petitioner, v. PEOPLE OF THE PHILIPPINES, Respondent.

  • G.R. No. 175651, September 14, 2016 - PILMICO-MAURI FOODS CORP., Petitioner, v. COMMISSIONER OF INTERNAL REVENUE, Respondent.

  • G.R. No. 218891, September 19, 2016 - EDMUND BULAUITAN Y MAUAYAN,* Petitioner, v. PEOPLE OF THE PHILIPPINES, Respondent.

  • G.R. No. 218009, September 21, 2016 - MARVIN G. FELIPE AND REYNANTE L. VELASCO, Petitioners, v. DANILO DIVINA TAMAYO KONSTRACT, INC. (DDTKI) AND/OR DANILO DIVINA TAMAYO, PRESIDENT/OWNER, Respondent.

  • A.C. No. 8560, September 06, 2016 - CARRIE-ANNE SHALEEN CARLYLE S. REYES, Complainant, v. ATTY. RAMON F. NIEVA, Respondent.