

|
|
|
|
|
ROBLETT
INDUSTRIAL CONSTRUCTION CORPORATION,
G. R. No. 116682
January 2, 1997
-versus-
COURT
OF APPEALS and CONTRACTORS EQUIPMENT
CORPORATION,
BELLOSILLO, J.:
On 23 September
1986 respondent Contractors Equipment
Corporation [CEC] instituted an action for a sum of money against
petitioner
Roblett Industrial Construction Corporation [RICC] before the Regional
Trial Court of Makati alleging that in 1985 it leased to the latter
various
construction equipment which it used in its projects. As a result RICC
incurred unpaid accounts amounting to P342,909.38. On 19 December
1985 RICC through its Assistant Vice President for Finance Candelario
S.
Aller Jr. entered into an Agreement[1]
with CEC where it confirmed petitioner's account. As an off-setting
arrangement
respondent received from petitioner construction materials worth
P115,000.00
thus reducing petitioner's balance to P227,909.38.
A day before the execution of their Agreement or on 18 December 1985, RICC paid CEC P10,000.00 in postdated checks which when deposited were dishonored. As a consequence, the latter debited the amount to petitioner's account of P227,909.38, thus, increasing its balance to P237,909.38. On 24 July 1986 Mariano R. Manaligod Jr., General Manager of CEC, sent a letter of demand to petitioner through its Vice President for Finance regarding the latter's overdue account of P237,909.38 and sought settlement thereof on or before 31 July 1986. In reply, petitioner requested for thirty [30] days to have enough time to look for funds to substantially settle its account. Traversing the allegations of respondent, Candelario S. Aller Jr. declared that he signed the Agreement with the real intention of having proof of payment. In fact Baltazar Banlot, Vice President for Finance of petitioner, claimed that after deliberation and audit it appeared that petitioner overpaid respondent by P12,000.00 on the basis of the latter's Equipment Daily Time Reports for 2 May to 14 June 1985 which reflected a total obligation of only P103,000.00. He claimed however that the Agreement was not approved by the Board and that he did not authorize Aller Jr. to sign thereon. On rebuttal, Manaligod Jr. declared that petitioner had received a statement of account covering the period from 28 March to 12 July 1985 in the amount of P376,350.18 which it never questioned. From this amount P3,440.80, based on respondent's account with petitioner and P30,000.00, representing payments made by the latter, were deducted thus leaving a balance of P342,909.38 as mentioned in the Agreement. On 19 December 1990 the trial court rendered judgment ordering petitioner to pay respondent: (a) P237,909.38 plus legal interest from 31 July 1986 until full payment; (b) P2,000.00 as litigation expenses; (c) 20% of the sum due and payable as attorney's fees; and (d) cost of suit.[2] Its ruling is anchored on its finding that:
On 29 July 1994 respondent Court of Appeals affirmed the decision of the trial court.[4] Petitioner imputes the following errors to respondent court: [1] in not holding that, insofar as it fixed petitioner's alleged obligation to respondent at P342,909.38, the Agreement is unenforceable for being in the nature of an unauthorized contract; and, [2] in not holding that petitioner's obligation to respondent had been fully paid and that petitioner even overpaid respondent by P12,000.00. As regards the first error, petitioner asserts that the Agreement is unenforceable for having been executed by Candelario S. Aller Jr. without authority. Significantly, in the proceedings before respondent Court of Appeals, petitioner assigned a lone error allegedly committed by the trial court, i.e., full payment, if not overpayment by P12,000.00, of the obligation referred to in the second issue raised in the petition therein. Quite obviously, having limited itself to that particular issue to the exclusion of any other, petitioner can no longer be permitted to assail the finding of the trial court on the validity of the Agreement.[5] As regards the factual issue on the correctness of the amount of petitioner's obligation, or whether it has been fully paid, petitioner insists that from a perusal of Exhs. "2," "2-A" to "2-Z" all of which refer to respondent's Equipment Daily Time Reports for 2 May to 14 June 1985, it was established that the equipment leased was actually used for only 191 hours. Multiplying 191 hours by the rental rate of P540.00 per hour will amount to P103,140.00 which is petitioner's correct rental obligation to respondent. Taking into account the construction materials worth P115,000.00 received by respondent from petitioner an overpayment of P12,000.00 more or less results. In the absence of any showing that the trial court failed to appreciate facts and circumstances of weight and substance that would have altered its conclusion, no compelling reason exists for this Court to impinge upon matters more appropriately within its province.[6] Consequently, we sustain the finding of the trial court that the evidence relied upon by petitioner is incomplete as it does not reflect the entire period of the lease agreement which, on the basis of respondent's evidence, covered the period of 28 March to 12 July 1985. Furthermore, estoppel in pais arises when one, by his acts, representations or admissions, or by his own silence when he ought to speak out, intentionally or through culpable negligence, induces another to believe certain facts to exist and such other rightfully relies and acts on such belief, so that he will be prejudiced if the former is permitted to deny the existence of such facts.[7] This doctrine obtains in the present case. A statement of account for P376,350.18 covering the period above mentioned was received from respondent by petitioner with nary a protest from the latter. Neither did petitioner controvert the demand letter concerning the overdue account of P237,909.38; on the contrary, it asked for ample time to source funds to substantially settle the account. WHEREFORE, the petition is DENIED. The decision of respondent Court of Appeals dated 29 July 1994 affirming that of the Regional Trial Court of Makati dated 19 December 1990 is AFFIRMED. Costs against petitioner. SO ORDERED. Padilla, Vitug, Kapunan and Hermosisima, Jr., JJ., concur. ___________________________
[2] Decision penned by Judge Ignacio M. Capulong, NCJR, RTC Br. 134, Makati, Metro Manila, Rollo, p. 25. [3] Rollo, p. 24. [4] Decision penned by Justice Serafin V. C. Guingona, concurred in by Justices Gloria C. Paras and Eubulo G. Verzola; Rollo, p. 38. [5] See Compañia Maritima v. Court of Appeals, G. R. No. 50900, 9 April 1985, 135 SCRA 593. [6] People v. Caras, G. R. No. 112731, 18 July 1994, 234 SCRA 199. [7] Panay Electric Co. v. Court of Appeals, G. R. No. 81939, 29 June 1989, 174 SCRA 500. |
|
Search the Chan Robles Virtual Law Library The Home of the Philippine On-Line Legal Resources |
|
|
|
|
|
|