CHANROBLES VIRTUAL LAW LIBRARY
US LAWS, STATUTES and CODES : Chan Robles Virtual Law Library USA Supreme Court Decisions | Resolutions : Chan Robles Virtual Law Library

ChanRobles™ Virtual Law Library™ | chanrobles.com™   
Main Index Repository of Laws, Statutes and Codes Latest Philippine Supreme Court Decisions Chan Robles Virtual Law Library Latest Legal Updates Philippine Legal Resources Significant Philippine Legal Resources Worldwide Legal Resources Philippine Supreme Court Decisions United States Legal Resources United States Supreme Court Jurisprudence ChanRobles LawTube - Social Network

ChanRobles Internet Bar Review : www.chanroblesbar.com DebtKollect Company, Inc. - Debt Collection Firm Intellectual Property Division - Chan Robles Law Firm

Philippine Supreme Court DecisionsChanRobles On-Line Bar Review

google search for chanrobles.comSearch for www.chanrobles.com


UNITED STATES V. CALIFORNIA BRIDGE & CONSTR. CO., 245 U. S. 337 (1917)

Subscribe to Cases that cite 245 U. S. 337 RSS feed for this section

U.S. Supreme Court

United States v. California Bridge & Constr. Co., 245 U.S. 337 (1917)

United States v. California Bridge & Construction Company

Nos. 39, 40

Argued November 9, 12, 1917

Decided December 10, 1917

245 U.S. 337

Syllabus

Claimant entered into a contract with the United States to erect certain structures "at the United States navy yard, Mare Island." Held, upon the facts, as found by the court below, that the site selected before the execution of the contract was selected provisionally, and subject to be changed by the government for some other location within the navy yard, and that claimant so understood when the contract was made.

A judgment exonerating a surety on a government construction contract, upon the ground that the location of the work was changed by the United States without the surety's consent, is not res judicata in respect of the right of the United States to make the change as against the principal contractor when the latter was not a party to the action in which the judgment was rendered and when the right is dependent not upon the terms of the written contract, but upon notice and representations aliunde which, in the case of the surety, chanroblesvirtualawlibrary

Page 245 U. S. 338

may have been different, and so have produced a different understanding, than in the case of the principal.

Having annulled a construction contract for default, the United States relet the contract at higher cost. Under supplemental agreements with the new contractor, certain deviations from the contract were made, involving a cost of about 6% of the total contract price and requiring estimates of the attendant expenses. Notwithstanding that these changes, on the whole, reduced the cost of the work, held, because of the deviations, that the difference between the cost and the original contract price was not a proper measure of the original contractor's liability.

In view of the history of the negotiation preceding the contract here in question, held that it would be highly inequitable to allow the government's claim of liquidated damages.

50 Ct.Clms. 40 affirmed.

The cases are stated in the opinion.





Back
ChanRobles™ LawTube

google search for chanrobles.com Search for www.chanrobles.com


Supreme Court Decisions Philippine Supreme Court DecisionsUS Supreme Court Decisions



www.chanrobles.us




QUICK SEARCH

cralaw

Browse By ->> Volume


cralaw

Browse By ->> Year


cralaw

  Copyright © ChanRobles Publishing Company | Disclaimer | E-mail Restrictions
ChanRobles™ Virtual Law Library | chanrobles.com™
 
RED