Midland Land & Improvement Co. v. United States, 270 U.S. 251 (1926)

Midland Land & Improvement Company v. United States

No. 105

Argued January 8, 1926

Decided March 1, 1926

270 U.S. 251

Syllabus

Where a contractor, though not in default, abandons the work and refuses to complete the contract, the government may relet the unfinished work to another and apply retained percentages towards recoupment of additional expenses so incurred.

58 Ct.Cls. 671 affirmed. chanrobles.com-red

Page 270 U. S. 252

Appeal from a judgment of the Court of Claims in favor of the United States in a suit to recover the amount of moneys retained by the government from payments made to the claimant on account of work done under a contract which the claimant afterwards abandoned.



























chanrobles.com



ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com