CHANROBLES VIRTUAL LAW LIBRARY
US LAWS, STATUTES and CODES : Chan Robles Virtual Law Library USA Supreme Court Decisions | Resolutions : Chan Robles Virtual Law Library

ChanRobles™ Virtual Law Library™ | chanrobles.com™   
Main Index Repository of Laws, Statutes and Codes Latest Philippine Supreme Court Decisions Chan Robles Virtual Law Library Latest Legal Updates Philippine Legal Resources Significant Philippine Legal Resources Worldwide Legal Resources Philippine Supreme Court Decisions United States Legal Resources United States Supreme Court Jurisprudence ChanRobles LawTube - Social Network

ChanRobles Internet Bar Review : www.chanroblesbar.com DebtKollect Company, Inc. - Debt Collection Firm Intellectual Property Division - Chan Robles Law Firm

Philippine Supreme Court DecisionsChanRobles On-Line Bar Review

google search for chanrobles.comSearch for www.chanrobles.com


UNITED STATES V. JOSEPH A. HOLPUCH CO., 328 U. S. 234 (1946)

Subscribe to Cases that cite 328 U. S. 234 RSS feed for this section

U.S. Supreme Court

United States v. Joseph A. Holpuch Co., 328 U.S. 234 (1946)

United States v. Joseph A. Holpuch Co.,

Nos. 696 and 697

Argued May 3, 1946

Decided May 20, 1946

328 U.S. 234

Syllabus

Respondent had two construction contracts with the United States, each of which provided that

"disputes concerning questions arising under this contract shall be decided by the contracting officer . . . subject to written appeal . . . to the head of the department."

Held:

1. Disputes as to extra pay for footing excavations and for increased wages paid to bricklayers were "questions arising under this contract" within the meaning of the quoted provision. Pp. 328 U. S. 238-239.

2. Respondent's failure to exhaust the administrative appeal provisions of the contracts barred recovery in the Court of Claims in respect of such disputes. P. 328 U. S. 239.

3. In the absence of clear evidence that the appeal procedure prescribed is inadequate or unavailable, that procedure must be pursued and exhausted before respondent may be heard to complain in a court. P. 328 U. S. 240.

4. The designation on the covers of the contracts of the disbursing officer who would make payment on the contracts was not a part of the contracts, and cannot be used in any way to alter or amend any actual provisions thereof. P. 328 U. S. 240. chanroblesvirtualawlibrary

Page 328 U. S. 235

5. Even if it be assumed that the dispute as to extra pay for footing excavations concerned only the amount of payment under the contract, such an issue is a question "arising under" the contract, and therefore expressly subject to the administrative appeal provision. P. 328 U. S. 241.

6. There being no evidence that the wage increase to bricklayers was established by the Federal Emergency Administration of Public Works, which, under the contracts, was the only agency that had authority to do so, a provision for an automatic adjustment of the amount due the contractor in that event did not become operative. P. 328 U. S. 242.

104 Ct.Cls. 254, reversed.

The respondent brought two suits in the Court of Claims on two contracts with the United States, and was adjudged entitled to recover on both. This Court granted certiorari. 327 U.S. 772. Reversed, p. 328 U. S. 243.





Back
ChanRobles™ LawTube

google search for chanrobles.com Search for www.chanrobles.com


Supreme Court Decisions Philippine Supreme Court DecisionsUS Supreme Court Decisions



www.chanrobles.us




QUICK SEARCH

cralaw

Browse By ->> Volume


cralaw

Browse By ->> Year


cralaw

  Copyright © ChanRobles Publishing Company | Disclaimer | E-mail Restrictions
ChanRobles™ Virtual Law Library | chanrobles.com™
 
RED