49 C.F.R. § 195.214 Welding procedures.
Title 49 - Transportation
(a) Welding must be performed by a qualified welder in accordance with welding procedures qualified under Section 5 of API 1104 or Section IX of the ASME Boiler and Pressure Vessel Code (ibr, see §195.3) . The quality of the test welds used to qualify the welding procedure shall be determined by destructive testing. (b) Each welding procedure must be recorded in detail, including the results of the qualifying tests. This record must be retained and followed whenever the procedure is used. [Amdt. 195–38, 51 FR 20297, June 4, 1986, as amended at Amdt. 195–81, 69 FR 32897, June 14, 2004]
Title 49: Transportation
PART 195—TRANSPORTATION OF HAZARDOUS LIQUIDS BY PIPELINE
Subpart D—Construction
§ 195.214 Welding procedures.