§ 5328. —  Project review.


[Laws in effect as of January 7, 2003]
[Document not affected by Public Laws enacted between
  January 7, 2003 and December 19, 2003]
[CITE: 49USC5328]

 
                        TITLE 49--TRANSPORTATION
 
              SUBTITLE III--GENERAL AND INTERMODAL PROGRAMS
 
                     CHAPTER 53--MASS TRANSPORTATION
 
Sec. 5328. Project review

    (a) Schedule.--(1) When the Secretary of Transportation allows a new 
fixed guideway project to advance into the alternatives analysis stage 
of project review, the Secretary shall cooperate with the applicant in 
alternatives analysis and in preparing a draft environmental impact 
statement and shall approve the draft for circulation not later than 45 
days after the applicant submits the draft to the Secretary.
    (2) After the draft is circulated and not later than 30 days after 
the applicant selects a locally preferred alternative, the Secretary 
shall allow the project to advance to the preliminary engineering stage 
if the Secretary finds the project is consistent with section 5309(e).
    (3) The Secretary shall issue a record of decision and allow a 
project to advance to the final design stage of construction not later 
than 120 days after the final environmental impact statement for the 
project is completed.
    (4) The Secretary shall make a full funding grant agreement under 
section 5309 of this title for a project not later than 120 days after 
the project enters the final design stage of construction. The agreement 
shall provide for a United States Government share of the construction 
cost at least equal to the Government share estimated in the Secretary's 
most recent report required under 5309(o)(1) \1\ or an update of the 
report unless the applicant requests otherwise.
---------------------------------------------------------------------------
    \1\ So in original. Probably should be ``section 5309(o)(1)''.
---------------------------------------------------------------------------
    (b) Allowed Delays.--(1) Advancement of a project under the time 
requirements of subsection (a) of this section may be delayed only--
        (A) for the time the applicant may request; or
        (B) during the time the Secretary finds, after reasonable notice 
    and an opportunity for comment, that the applicant, for reasons 
    attributable only to the applicant, has not complied substantially 
    with the provisions of this chapter applicable to the project.

    (2) Not more than 10 days after imposing a delay under paragraph 
(1)(B) of this subsection, the Secretary shall give the applicant a 
written statement explaining the reasons for the delay and describing 
actions the applicant must take to end the delay.
    (3) At least once every 6 months, the Secretary shall report to the 
Committee on Transportation and Infrastructure of the House of 
Representatives and the Committee on Banking, Housing, and Urban Affairs 
of the Senate on each situation in which the Secretary has not met a 
time requirement of subsection (a) of this section or delayed a time 
requirement under paragraph (1)(B) of this subsection. The report shall 
explain the reasons for the delay and include a plan for achieving 
timely completion of the Secretary's review.
    (c) Program of Interrelated Projects.--(1) In this subsection, a 
program of interrelated projects includes the following:
        (A) the New Jersey Urban Core Project (as defined in title III 
    of the Intermodal Surface Transportation Efficiency Act of 1991 
    (Public Law 102-240, 105 Stat. 2087)).
        (B) the San Francisco Bay Area Rail Extension Program, 
    consisting of at least an extension of the San Francisco Bay Area 
    Rapid Transit District to the San Francisco International Airport 
    (Phase 1a to Colma and Phase 1b to San Francisco Airport), the Santa 
    Clara County Transit District Tasman Corridor Project, a program 
    element designated by a change to the Metropolitan Transportation 
    Commission Resolution No. 1876, and a program element financed 
    completely with non-Government amounts, including the BART Warm 
    Springs Extension, Dublin Extension, and West Pittsburg Extension.
        (C) the Los Angeles Metro Rail Minimum Operable Segment-3 
    Program, consisting of 7 stations and approximately 11.6 miles of 
    heavy rail subway on the following lines:
            (i) one line running west and northwest from the Hollywood/
        Vine station to the North Hollywood station, with 2 intermediate 
        stations.
            (ii) one line running west from the Wilshire/Western station 
        to the Pico/San Vicente station, with one intermediate station.
            (iii) the East Side Extension, consisting of an initial line 
        of approximately 3 miles, with at least 2 stations, beginning at 
        Union Station and running generally east.

        (D) the Baltimore-Washington Transportation Improvement Program, 
    consisting of 3 extensions of the Baltimore Light Rail to Hunt 
    Valley, Penn Station, and Baltimore-Washington Airport, MARC 
    extensions to Frederick and Waldorf, Maryland, and an extension of 
    the Washington Subway system to Largo, Maryland.
        (E) the Tri-County Metropolitan Transportation District of 
    Oregon Light Rail Program, consisting of the locally preferred 
    alternative for the Westside Light Rail Project, including system 
    related costs, contained in the Department of Transportation and 
    Related Agencies Appropriations Act, 1991 (Public Law 101-516, 104 
    Stat. 2155), and defined in House Report 101-584, the Hillsboro 
    extension to the Westside Light Rail Project contained in that Act, 
    and the locally preferred alternative for the South/North Corridor 
    Project.
        (F) the Queens Local/Express Connector Program, consisting of 
    the locally preferred alternative for the connection of the 63d 
    Street tunnel extension to the Queens Boulevard lines, the bell-
    mouth part of the connector that will allow for future access by 
    commuter rail trains and other subway lines to the 63d Street tunnel 
    extension, planning elements for connecting the upper and lower 
    levels to commuter and subway lines in Long Island City, and 
    planning elements for providing a connector for commuter rail 
    transportation to the East side of Manhattan and subway lines to the 
    proposed Second Avenue subway.
        (G) the Dallas Area Rapid Transit Authority light rail elements 
    of the New System Plan, consisting of the locally preferred 
    alternative for the South Oak Cliff corridor, the South Oak Cliff 
    corridor extension-Camp Wisdom, the West Oak Cliff corridor-
    Westmoreland, the North Central corridor-Park Lane, the North 
    Central corridor-Richardson, Plano, and Garland extensions, the 
    Pleasant Grove corridor-Buckner, and the Carrollton corridors-
    Farmers Branch and Las Colinas terminal.
        (H) other programs designated by law or the Secretary.

    (2) Consistent with the time requirements of subsection (a) of this 
section or as otherwise provided by law, the Secretary shall make at 
least one full financing grant agreement for each program described in 
paragraph (1) of this subsection. The agreement shall include 
commitments to advance each of the applicant's program elements (in the 
program of interrelated projects) through the appropriate program review 
stages as provided in subsection (a) or as otherwise provided by law and 
to provide Government financing for each element. The agreement may be 
changed to include design and construction of a particular element.
    (3) When reviewing a project in a program of interrelated projects, 
the Secretary shall consider the local financial commitment, 
transportation effectiveness, and other assessment factors of all 
program elements to the extent consideration expedites carrying out the 
project.
    (4) Including a program element not financed by the Government in a 
program of interrelated projects does not impose Government requirements 
that otherwise would not apply to the element.

(Pub. L. 103-272, Sec. 1(d), July 5, 1994, 108 Stat. 828; Pub. L. 104-
205, title III, Sec. 336, Sept. 30, 1996, 110 Stat. 2974; Pub. L. 104-
287, Sec. 5(9), Oct. 11, 1996, 110 Stat. 3389; Pub. L. 105-178, title 
III, Sec. 3009(h)(2), (3)(B), (C), June 9, 1998, 112 Stat. 356; Pub. L. 
105-206, title IX, Sec. 9009(h)(2), (3), July 22, 1998, 112 Stat. 856.)

                                          Historical and Revision Notes
----------------------------------------------------------------------------------------------------------------
           Revised  Section                    Source (U.S. Code)               Source (Statutes at Large)
----------------------------------------------------------------------------------------------------------------
5328(a)...............................  49 App.:1602(a)(6).              July 9, 1964, Pub. L. 88-365, 78 Stat.
                                                                          302, Sec.  3(a)(6)-(8); added Jan. 6,
                                                                          1983, Pub. L. 97-424, Sec.  304(b), 96
                                                                          Stat. 2150; restated Dec. 18, 1991,
                                                                          Pub. L. 102-240, Sec.  3011(a), 105
                                                                          Stat. 2095.
5328(b)...............................  49 App.:1602(a)(7).
5328(c)(1)............................  49 App.:1602(a)(8)(C).
5328(c)(2)............................  49 App.:1602(a)(8)(A) (1st-3d
                                         sentences).
5328(c)(3)............................  49 App.:1602(a)(8)(B).
5328(c)(4)............................  49 App.:1602(a)(8)(A) (last
                                         sentence).
----------------------------------------------------------------------------------------------------------------

    In subsection (a)(1), the words ``the date on which'' are omitted as 
surplus.
    In subsection (a)(2), the words ``the criteria set forth in'' are 
omitted as surplus.
    In subsection (a)(4), the words ``negotiate and'' are omitted as 
surplus. The words ``under section 5309 of this title'' are added for 
clarity.
    In subsection (b)(1)(A), the words ``solely at the applicant's 
discretion'' are omitted as surplus.
    In subsection (c)(2), the words ``if appropriate'' are omitted as 
surplus.

                       References in Text

    The Intermodal Surface Transportation Efficiency Act of 1991, 
referred to in subsec. (c)(1)(A), is Pub. L. 102-240, Dec. 18, 1991, 105 
Stat. 1914, as amended. Title III of the Act is also known as the 
Federal Transit Act Amendments of 1991. Provisions defining the New 
Jersey Urban Core Project are contained in section 3031 of the Act, 
which is not classified to the Code. For complete classification of this 
Act to the Code, see Short Title of 1991 Amendment note set out under 
section 101 of this title and Tables.
    The Department of Transportation and Related Agencies Appropriations 
Act, 1991, referred to in subsec. (c)(1)(E), is Pub. L. 101-516, Nov. 5, 
1990, 104 Stat. 2155, as amended. Provisions relating to the Westside 
Light Rail Program are contained in section 328 of the Act, which is not 
classified to the Code. For complete classification of this Act to the 
Code, see Tables.


                               Amendments

    1998--Subsec. (a)(2). Pub. L. 105-178, Sec. 3009(h)(2), substituted 
``5309(e)'' for ``5309(e)(1)-(6) of this title''.
    Subsec. (a)(4). Pub. L. 105-178, Sec. 3009(h)(3)(C), as added by 
Pub. L. 105-206, Sec. 9009(h)(3), substituted ``5309(o)(1)'' for 
``section 5309(m)(2) of this title''.
    Pub. L. 105-178, Sec. 3009(h)(3)(B), as amended by Pub. L. 105-206, 
Sec. 9009(h)(2), substituted ``full funding'' for ``full financing''.
    1996--Subsec. (b)(3). Pub. L. 104-287 substituted ``Transportation 
and Infrastructure'' for ``Public Works and Transportation''.
    Subsec. (c)(1)(E). Pub. L. 104-205 struck out ``Westside'' after 
``District of Oregon'' and ``and'' after ``House Report 101-584,'' and 
inserted before period at end ``, and the locally preferred alternative 
for the South/North Corridor Project''.


                    Effective Date of 1998 Amendment

    Title IX of Pub. L. 105-206 effective simultaneously with enactment 
of Pub. L. 105-178 and to be treated as included in Pub. L. 105-178 at 
time of enactment, and provisions of Pub. L. 105-178, as in effect on 
day before July 22, 1998, that are amended by title IX of Pub. L. 105-
206 to be treated as not enacted, see section 9016 of Pub. L. 105-206, 
set out as a note under section 101 of Title 23, Highways.

                  Section Referred to in Other Sections

    This section is referred to in section 5333 of this title.






























chanrobles.com





ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com