48 C.F.R. PART 815—CONTRACTING BY NEGOTIATION


Title 48 - Federal Acquisition Regulations System


Title 48: Federal Acquisition Regulations System

Browse Previous |  Browse Next

PART 815—CONTRACTING BY NEGOTIATION

Section Contents

Subpart 815.5—Unsolicited Proposals

815.504   Advance guidance.
815.506   Department procedures.
815.506-1   Receipt and initial review.

Subpart 815.6—Source Selection

815.607   Disclosure of mistakes before award.

Subpart 815.8—Price Negotiation

815.804-70   Preproduction and start-up and other nonrecurring costs.
815.805-4   Technical analysis.


Authority:  38 U.S.C. 501 and 40 U.S.C. 486(c).

Source:  49 FR 12604, Mar. 29, 1984, unless otherwise noted.

Subpart 815.5—Unsolicited Proposals
top

Source:  51 FR 6005, Feb. 19, 1986, unless otherwise noted.

815.504   Advance guidance.
top

(a) Any inquiries from a potential offeror of an unsolicited proposal shall be referred to the appropriate VA contact point designated in 815.506(a). The contact point will determine the nature of the potential proposal and determine what technical/professional disciplines need be consulted to determine the VA need for such a proposal and the likelihood that a formal proposal would be favorably reviewed. In consultation with such technical/professional offices, the VA contact point will inform the potential proposer of any additional information required to provide advance guidance as well as the information specified in FAR 15.504.

(b) The FAR contact point will maintain a record of advance guidance provided and the disposition/recommendation regarding the potential offer.

815.506   Department procedures.
top

(a) The Chief, Acquisition and Materiel Management Service, servicing the field facility and the Director, VA Marketing Center, Hines, Illinois are designated as the VA contact points for unsolicited proposals submitted at the facility level. The Deputy Assistant Secretary for Acquisition and Materiel Management is designated as the VA contact point for all unsolicited proposals received at VA Central Office.

(b) Each unsolicited proposal received by the Department of Veterans Affairs will be submitted to the appropriate contact point.

(c) The VA contact point will review the unsolicited proposal and ensure that it is complete as prescribed in FAR 15.505. If required information is not submitted, the VA contact point will:

(1) Determine if advance guidance as specified in FAR 15.504 is necessary (2) request that the offeror provide the necessary information if it is determined that the formal evaluation prescribed in FAR 15.506–2 is appropriate; and (3) establish an estimated due date for completion of the review process.

[51 FR 6005, Feb. 19, 1986, as amended at 54 FR 40063, Sept. 29, 1989; 54 FR 42508, Oct. 17, 1989]

815.506-1   Receipt and initial review.
top

(a) When VA contact point determines that a comprehensive evaluation is to be undertaken (i.e., the proposal complies with the requirements in FAR 15.506–1(a) and is related to the mission of VA), the offeror will be contacted to ensure that all data that should be restricted in accordance with FAR 15.509 has been identified.

(b) The VA contact point will maintain a log of all unsolicited proposals which will be evaluated. The log will indicate:

(1) The date the proposal was received;

(2) The date that the unsolicited proposal has been determined to warrant a comprehensive evaluation;

(3) A description of the proposal;

(4) The offices requested to evaluate the proposal and the date such offices are requested to return their evaluations;

(5) The date the reviewing offices finalize their respective evaluation; and

(6) The final disposition of the proposal.

(c) Each office which is assigned responsibility for reviewing an unsolicited proposal will be advised of the need to evaluate the proposal against the criteria set forth in FAR 15.507(a) (1) through (3), i.e., is the proposal available to the Government without restriction from another source, does it closely resemble a pending competitive acquisition, is the proposal lacking in demonstrated innovation or uniqueness? If the reviewers conclude in the affirmative as to any one of these questions, the VA contact point shall be advised and return the proposal to the proposer.

(d) With regard to an unsolicited proposal being processed at a field facility, if the reviewing offices conclude that the unsolicited proposal should be accepted and provide the justification and certification required by FAR 15.507, the VA contact point will obtain the prior approval of the Deputy Assistant Secretary for Acquisition and Materiel Management (93) prior to proceeding with negotiation. In order to obtain the approval, the VA contact point will submit all necessary documentation supporting the noncompetitive negotiation including any justification and approval required by FAR Subpart 6.3 and results of any synopsis required by FAR Subpart 5.2 The Deputy Assistant Secretary for Acquisition and Materiel Management will coordinate the proposal with the cognizant VA Central Office program official(s) and furnish the VA contact point with the final decision.

(e) All copies of the unsolicited proposal will be controlled by the contact point by numbering each copy. If a reviewing office requires additional copies, the reviewing office will obtain approval of the VA contact point prior to duplication, numbering the copies as specified by the contact point. All copies will be returned to the VA contact point once review is completed.

[51 FR 6005, Feb. 19, 1986, as amended at 54 FR 40063, Sept. 29, 1989]

Subpart 815.6—Source Selection
top
815.607   Disclosure of mistakes before award.
top

The Head of the Contracting Activity (as defined in 802.1) is delegated authority to permit correction of mistakes in proposals before award consistent with FAR 15.607.

[54 FR 45736, Oct. 31, 1989]

Subpart 815.8—Price Negotiation
top
815.804-70   Preproduction and start-up and other nonrecurring costs.
top

In evaluating start-up and other nonrecurring costs, the extent to which these costs are included in the proposed price and the intent to absorb or recover any such costs in any future noncompetitive procurement or other pricing action will be determined. The contracting officer will ascertain, with the assistance of the Assistant Inspector General for Policy, Planning and Resources (53), as required or considered necessary, that payment of such costs is not duplicated. For example, cost of equipment paid for by the Government through a setup or connection agreement will not be included in depreciation costs of a subsequently negotiated agreement.

[49 FR 12604, Mar. 29, 1984, as amended at 50 FR 792, Jan. 7, 1985; 54 FR 40063, Sept. 29, 1989]

815.805-4   Technical analysis.
top

(a) Contracting officers are responsible for the technical and administrative sufficiency of the contracts they enter into and ensuring that all legal and technical reviews are accomplished. To this end, initial and revised pricing of all negotiated prime contracts (including subcontract pricing under them) and contract modifications will be subject to technical analyses to the degree the contracting officer deems necessary (see 801.602–70 for required legal reviews). Technical analyses of the proposals will be requested by the contracting officer from the appropriate technical personnel to address, as a minimum, the items set forth in FAR Subpart 15.805–4. Contracting officers shall not begin negotiation of or award any negotiated contracts or contract modifications before receipt, analysis and consideration of documented technical evaluations for every procurement action requiring such analysis under the conditions prescribed in FAR 15.805–4. The results of such analyses will be documented in the contract file and will also be made available to the auditor performing the preaward audit required by 815.805–5.

(b) When, in the opinion of the contracting officer, the complexity of the proposed contract warrants, he/she will submit the proposed contract to the Deputy Assistant Secretary for Acquisition and Materiel Management (93) for review and comment. When deemed advisable, the Deputy Assistant Secretary for Acquisition and Materiel Management (93) will request the General Counsel to accomplish a legal review. This review is in addition to the legal review specified in 801.602–70.

Browse Previous |  Browse Next

chanrobles.com





ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com