49 C.F.R. PART 236--RULES, STANDARDS, AND INSTRUCTIONS GOVERNING THE INSTALLATION, INSPECTION, MAINTENANCE, AND REPAIR OF SIGNAL AND TRAIN CONTROL SYSTEMS, DEVICES, AND APPLIANCES
TITLE 49--Transportation
Subtitle B--OTHER REGULATIONS RELATING TO TRANSPORTATION
CHAPTER II--FEDERAL RAILROAD ADMINISTRATION, DEPARTMENT OF TRANSPORTATION
PART 236--RULES, STANDARDS, AND INSTRUCTIONS GOVERNING THE INSTALLATION, INSPECTION, MAINTENANCE, AND REPAIR OF SIGNAL AND TRAIN CONTROL SYSTEMS, DEVICES, AND APPLIANCES
|
Applicability, minimum requirements, and penalties.
|
|
Subpart A--RULES AND INSTRUCTIONS: ALL SYSTEMS
|
Locking of signal apparatus housings.
|
|
|
Interference with normal functioning of device.
|
|
|
Design of control circuits on closed circuit principle.
|
|
|
Hand-operated switch equipped with switch circuit controller.
|
|
|
Circuit controller operated by switch-and-lock movement.
|
|
|
Operating characteristics of electromagnetic, electronic, or electrical apparatus.
|
|
|
Selection of circuits through indicating or annunciating instruments.
|
|
|
Electric locks, force drop type; where required.
|
|
|
Adjustment, repair, or replacement of component.
|
|
|
Spring switch signal protection; where required.
|
|
|
Spring switch; selection of signal control circuits through circuit controller.
|
|
|
Spring switch signal protection; requirements.
|
|
|
Electric lock, main track releasing circuit.
|
|
|
Pipe for operating connections, requirements.
|
|
|
Software management control plan.
|
|
|
Location of roadway signals.
|
|
|
Semaphore signal arm; clearance to other objects.
|
|
|
Spacing of roadway signals.
|
|
|
Buffing device, maintenance.
|
|
|
Track circuit requirements.
|
|
|
Track circuit feed at grade crossing.
|
|
|
Minimum length of track circuit.
|
|
|
Dead section; maximum length.
|
|
|
Turnout, fouling section.
|
|
|
Switch shunting circuit; use restricted.
|
|
|
Signal wires on pole line and aerial cable.
|
|
|
Open-wire transmission line; clearance to other circuits.
|
|
|
Protection of insulated wire; splice in underground wire.
|
|
|
Tagging of wires and interference of wires or tags with signal apparatus.
|
|
|
Purpose of inspection and tests; removal from service of relay or device failing to meet test requirements.
|
|
|
Semaphore or searchlight signal mechanism.
|
|
|
Switch circuit controller or point detector.
|
|
|
Insulation resistance tests, wires in trunking and cables.
|
|
|
Time releases, timing relays and timing devices.
|
|
Subpart B--AUTOMATIC BLOCK SIGNAL SYSTEMS
|
Track-circuit control of signals.
|
|
|
Signal governing movements over hand-operated switch.
|
|
|
Hand operated crossover between main tracks; protection.
|
|
|
Track signaled for movements in both directions, requirements.
|
|
|
Signal control circuits; requirements.
|
|
|
Battery or power supply with respect to relay; location.
|
|
|
Electric lock on hand-operated switch; control.
|
|
Subpart C--INTERLOCKING
|
Where signals shall be provided.
|
|
|
Track circuits and route locking.
|
|
|
Control circuits for signals, selection through circuit controller operated by switch points or by switch locking mechanism.
|
|
|
Mechanical locking or same protection effected by circuits.
|
|
|
Approach or time locking.
|
|
|
Facing point lock or switch-and-lock movement.
|
|
|
Mechanical or electric locking or electric circuits; requisites.
|
|
|
Loss of shunt protection; where required.
|
|
|
Signal governing approach to home signal.
|
|
|
Signal control circuits, selection through track relays or devices functioning as track relays and through signal mechanism contacts and time releases at automatic interlocking.
|
|
|
Movable bridge, interlocking of signal appliances with bridge devices.
|
|
|
Electric lock for hand-operated switch or derail.
|
|
|
Mechanical locking removed or disarranged; requirement for permitting train movements through interlocking.
|
|
|
Switch, movable-point frog or split-point derail.
|
|
|
Plunger of facing-point lock.
|
|
|
Locking dog of switch-and-lock movement.
|
|
|
Dogs, stops and trunnions of mechanical locking.
|
|
|
Locking faces of mechanical locking; fit.
|
|
|
Mechanical locking required in accordance with locking sheet and dog chart.
|
|
|
Mechanical locking, maintenance requirements.
|
|
|
Electromechanical interlocking machine; locking between electrical and mechanical levers.
|
|
|
Latch shoes, rocker links, and quadrants.
|
|
|
Switch circuit controller.
|
|
|
Valve locks, valves, and valve magnets.
|
|
|
Restoring feature on power switches.
|
|
Subpart D--TRAFFIC CONTROL SYSTEMS
|
Automatic block signal system and interlocking standards applicable to traffic control systems.
|
|
|
Signals controlled by track circuits and control operator.
|
|
|
Signals at controlled point.
|
|
|
Signals at adjacent control points.
|
|
|
Track signaled for movements in both directions, change of direction of traffic.
|
|
|
Approach or time locking; where required.
|
|
|
Locking, hand-operated switch; requirements.
|
|
|
Interlocking rules and instructions applicable to traffic control systems.
|
|
|
Interlocking inspections and tests applicable to traffic control systems.
|
|
Subpart E--AUTOMATIC TRAIN STOP, TRAIN CONTROL AND CAB SIGNAL SYSTEMS
|
Forestalling device and speed control.
|
|
|
Automatic brake application, initiation by restrictive block conditions stopping distance in advance.
|
|
|
Automatic brake application; initiation when predetermined rate of speed exceeded.
|
|
|
Operation interconnected with automatic block-signal system.
|
|
|
Proper operative relation between parts along roadway and parts on locomotive.
|
|
|
Release of brakes after automatic application.
|
|
|
Brake application; full service.
|
|
|
Interference with application of brakes by means of brake valve.
|
|
|
Two or more locomotives coupled.
|
|
|
Cab signals controlled in accordance with block conditions stopping distance in advance.
|
|
|
Cab signal indication when locomotive enters block where restrictive conditions obtain.
|
|
|
Interconnection of cab signal system with roadway signal system.
|
|
|
Visibility of cab signals.
|
|
|
Roadway element not functioning properly.
|
|
|
Roadway element insulation resistance.
|
|
|
Restrictive condition resulting from open hand-operated switch; requirement.
|
|
|
Roadway element inductor; height and distance from rail.
|
|
|
Trip arm; height and distance from rail.
|
|
|
Strap iron inductor; use restricted.
|
|
|
Entrance to equipped territory; requirements.
|
|
|
Power supply voltage; requirement.
|
|
|
Insulation resistance; requirement.
|
|
|
Rate of pressure reduction; equalizing reservoir or brake pipe.
|
|
|
Repaired or rewound receiver coil.
|
|
|
Receiver; location with respect to rail.
|
|
|
Contact element, mechanical trip type; location with respect to rail.
|
|
|
Minimum rail current required.
|
|
|
Provision made for preventing operation of pneumatic brake-applying apparatus by double-heading cock; requirement.
|
|
|
Locomotive of each train operating in train stop, train control or cab signal territory; equipped.
|
|
|
Restrictions imposed when device fails and/or is cut out en route.
|
|
|
Difference between speeds authorized by roadway signal and cab signal; action required.
|
|
|
Test, acknowledgement, and cut-in circuits.
|
|
|
Daily or after trip test.
|
|
Subpart F--DRAGGING EQUIPMENT AND SLIDE DETECTORS AND OTHER SIMILAR PROTECTIVE DEVICES
|
Signals controlled by devices; location.
|
|
Subpart G--DEFINITIONS
|
Application, brake; full service.
|
|
|
Characteristics, operating.
|
|
|
Circuit, double wire; line.
|
|
|
Circuit, switch shunting.
|
|
|
Controller, circuit; switch.
|
|
|
Lock, electric, forced drop.
|
|
|
Movement, switch-and-lock.
|
|
|
Plunger, facing point lock.
|
|
|
Position, false restrictive.
|
|
|
Principle, closed circuit.
|
|
|
Signal, slotted mechanical.
|
|
|
Spectacle, semaphore arm.
|
|
|
Switch, electro-pneumatic.
|
|
|
System, automatic block signal.
|
|
|
System, automatic train control.
|
|
|
System, automatic train stop.
|
|
|
Valve, electro-pneumatic.
|
|
Subpart H--STANDARDS FOR PROCESSOR-BASED SIGNAL AND TRAIN CONTROL SYSTEMS
|
Railroad Safety Program Plan (RSPP).
|
|
|
Product Safety Plan (PSP).
|
|
|
Minimum performance standard.
|
|
|
Filing and approval of PSPs.
|
|
|
Implementation and operation.
|
|
|
Operations and Maintenance Manual.
|
|
|
Training and qualification program, general.
|
|
|
Task analysis and basic requirements.
|
|
|
Training specific to control office personnel.
|
|
|
Training specific to locomotive engineers and other operating personnel.
|
|
|
Training specific to roadway workers.
|
|